What is the average personnel requirement for an acre of light brush during clearing operations?

10 person days

15 person days

The average personnel requirement for clearing an acre of light brush is 15 person days. This figure is derived from industry standards and practices that take into account the type of vegetation, terrain, and the efficiency of the personnel involved. When managing light brush, the nature of the work typically requires enough manpower to effectively manage the clearing process while ensuring safety and efficiency.

In this context, "person days" refers to the amount of work one individual can accomplish in a day, which is essential for planning and resource allocation in firefighting and land management operations. By standardizing this requirement, agencies can create more accurate staffing and logistics plans to ensure thorough and effective operations in the field. Thus, recognizing that light brush clearing is less intensive compared to denser vegetation types, it aligns with the established average of 15 person days for this particular task.

Get further explanation with Examzify DeepDiveBeta

20 person days

25 person days

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy